Construction is underway in Snyder on an artificial intelligence infrastructure campus. The project, called Snyder AI, is being developed by Energy Vault Inc. for Crusoe Cloud.

Initial plans call for 8 megawatts of modular data center capacity, with a target operation date in early 2027. The site has potential for expansion, with plans for up to 500 megawatts of capacity. Energy Vault is purchasing modular data centers from Crusoe, which will then lease them back.

Construction currently includes site preparation, fiber installation, and power infrastructure work. Further details on the project are available from Energy Vault, including specifics on the phased expansion and campus design.